Paving contractors will begin street overlay and patching work in Cheney beginning on Monday, August 8. Specific areas will include:
Front Street
2nd Street, from D to B Street
Washington Street, W. 6th to 1st ST/SR-904
N 8th Street & Sunrise
Paving work is expected to take approximately 35 working days. Overall project work will include tree work, pavement grinding, patching, pre-leveling and paving, and
curb/sidewalk replacement. Street segments will be blocked off and motorists & pedestrians will have to find alternate routes.